Solar Power in India: Value Chain, Economics, Policy and Companies to Track

Profile picture of Karan Vijayvargiya
Karan Vijayvargiya · INH0000254708 Sep 2026 · 13 min read · Updated 8 Sep 2026, 10:53 am
Solar Power in India: Value Chain, Economics, Policy and Companies to Track

Data cutoff: 7 September 2026

Disclosure: This article is for education and research only. It is not investment advice or a recommendation to buy or sell any security.

In the first four parts of this series, we mapped the complete Indian power-sector value chain and then studied thermal power, hydropower and nuclear power.

If you have not read the earlier parts, you can start here:

Now we come to Part 5: Solar Power—the fastest-growing part of India's electricity system and a value chain that extends far beyond project developers.

India's solar market is entering a more difficult phase. Capacity is still growing quickly, but the investment question is no longer simply, "Who can build the most megawatts?" The better questions are:

  • Who can earn acceptable returns at competitive tariffs?
  • Which manufacturers can convert nameplate capacity into profitable production?
  • Who controls critical parts of the supply chain?
  • Which businesses can manage grid, storage, working-capital and policy risks?

This article maps the value chain, explains basic project economics, reviews the policy framework and provides a practical way to study listed companies.
 

1. India's solar market in numbers
 

India had 162.15 GW of installed solar capacity on 30 June 2026. This was 29.54% of India's total installed power capacity of 548.86 GW. [1]

This is an installed-capacity share, not a generation share. Solar plants generate only when sunlight is available, so their annual output is much lower than an equal amount of continuously available capacity. Investors should not use the 29.54% figure as solar's share of electricity generated.

India added 44.61 GW of solar capacity during FY2025-26, compared with 23.83 GW in the previous year. The official sector review reported 118.79 GW of large solar projects and 27.88 GW of rooftop solar by June 2026. [2] These two categories do not equal total solar capacity because the balance includes other reported categories, including off-grid and hybrid-related capacity.

The same official review reported about 172 GW of cumulative solar-module manufacturing nameplate capacity as of 31 March 2026. [2] Nameplate manufacturing capacity is not the same as annual production, dispatches or sales. Utilisation, technology, yields, cell availability, customer qualification and working capital determine how much of this capacity becomes profitable output.
 

2. The visible project pipeline is large, but must not be double-counted
 

As of 31 January 2026, the Central Electricity Authority reported: [3]

  • Standalone solar under construction: 64.67 GW
  • Standalone solar under tendering: 35.44 GW
  • Renewable hybrid projects under construction: 83.23 GW
  • Renewable hybrid projects under tendering: 10.08 GW

Hybrid projects may include wind, solar and storage. Their full capacity should not automatically be counted as additional solar capacity.

CEA's Generation Adequacy Plan models a power system with approximately 509 GW of solar, 80 GW of battery energy storage and 94 GW of pumped-storage capacity in 2035-36. [3] These are planning-model outcomes and likely system requirements, not unconditional commissioning targets or guaranteed demand.

As solar penetration rises, the value pool gradually moves from standalone generation towards storage and firm renewable power, transmission, forecasting, flexible generation, grid-management software and commercial and industrial power solutions.
 

3. The solar value chain

 

Upstream manufacturing

 

The upstream chain generally includes:

  1. Polysilicon
  2. Ingots
  3. Wafers
  4. Solar cells
  5. Modules
  6. Solar glass, encapsulants, backsheets, junction boxes and frames

India has expanded module and cell capacity rapidly, but upstream integration remains important. A company that assembles imported cells into modules has a different cost structure and policy exposure from a company that controls wafers, cells and modules.
 

Key manufacturing variables:
 

  • Capacity utilisation and process yield
  • Module and cell selling prices
  • Imported-input dependence
  • Technology mix, including TOPCon and HJT
  • Export exposure and customer qualification
  • Order-book quality and working capital
  • Capex funding and technology obsolescence

Midstream and downstream
 

The rest of the chain includes project development, land and approvals, PPAs, financing, EPC, inverters, trackers, cables, transformers, grid connectivity, operations and maintenance, rooftop solar, solar pumps, battery storage and hybrid projects.

These activities have different economics. A contracted developer should not be valued like a module manufacturer, and an EPC company should not be compared directly with a solar-glass producer.
 

4. How a solar project earns revenue
 

Annual generation = AC capacity x 8,760 hours x capacity-utilisation factor

For an illustrative 1 MW AC project operating at a 25% capacity-utilisation factor:
 

1 MW x 8,760 x 25% = 2,190 MWh per year

At an illustrative tariff of Rs 2.75 per kWh:

 

2,190,000 kWh x Rs 2.75 = approximately Rs 60.2 lakh of gross annual revenue per MW

A one-percentage-point change in capacity utilisation changes annual generation by 87.6 MWh per MW. At the same tariff, that changes gross annual revenue by approximately Rs 2.41 lakh per MW.
 

This is gross revenue, not EBITDA, cash flow or profit. A proper project model must include DC-to-AC sizing, degradation, auxiliary consumption, electrical losses, curtailment, availability, O&M, land cost, interest, receivable delays, taxes and storage cost.
 

CEA's planning assumptions show solar-PV capital cost declining from about Rs 4.5 crore per MW in 2025-26 to about Rs 4.0 crore per MW in 2035-36. [3] These are planning assumptions, not quotes for every project.

 

5. Policy framework

ALMM List-II for solar cells
 

ALMM rules affect which modules and cells can be used in covered projects. The solar-cell requirement under ALMM List-II became applicable from 1 June 2026.

 

A later MNRE decision created a limited exemption window for net-metering and open-access renewable projects, allowing eligible projects to commission without ALMM List-II cells until 31 December 2026. [4] This is not a general extension for every project category.
 

PIB reported that ALMM-listed domestic solar-cell capacity had reached 27 GW by March 2026. This is listed nameplate capacity, not proof of equivalent production, dispatches or utilisation.
 

ALMM List-III for ingots and wafers
 

MNRE has notified ALMM List-III for solar ingots and wafers to take effect from 1 June 2028. [5] The initial list is subject to specified domestic-supply conditions, including at least three independent manufacturers with combined capacity of 15 GW. The framework also contains cut-off and grandfathering provisions.

 

Production-linked incentives

 

The PLI programme for high-efficiency solar-PV modules has a total outlay of Rs 24,000 crore: Rs 4,500 crore under Tranche I and Rs 19,500 crore under Tranche II. [6] Incentives are linked to eligible production and sales for five years after commissioning.
 

An awarded capacity or announced plant is not automatically an operating, qualified and profitable facility.

 

Customs duties

India introduced Basic Customs Duty of 40% on imported modules and 25% on imported cells from April 2022. The structure was revised in the Union Budget 2025-26. The official note records a 20% tariff BCD for both modules and cells from 1 May 2025. It also records, from 2 February 2025, 20% BCD plus 20% AIDC for modules and 20% BCD plus 7.5% AIDC for cells, with nil SWS. [7]

 

Applicable landed cost may depend on classification, exemptions, trade-remedy duties and later notifications. Investors should use the latest CBIC notification for transaction-level analysis.
 

6. Demand-support programmes

PM Surya Ghar

 

PM Surya Ghar: Muft Bijli Yojana has an approved outlay of Rs 75,021 crore and aims to support rooftop solar for one crore households. The official review reported that more than 43 lakh households had been solarised by June 2026. [2]

 

Installations, sanctioned applications, vendor orders and subsidy disbursements should be treated as different metrics.
 

PM-KUSUM

 

PM-KUSUM supports decentralised plants, standalone solar pumps and solarisation of agricultural feeders and grid-connected pumps. The programme carries a stated target of 34.8 GW and central financial support of Rs 34,422 crore through FY2026-27. [2]
 

Renewable Consumption Obligation
 

The 35.95% obligation for FY2026-27 is an aggregate Renewable Consumption Obligation, not a solar-only target. The revised framework includes wind, hydro, distributed renewable energy and other renewable-energy components. [8]
 

7. Solar parks, transmission and storage

 

The government reported 54 sanctioned solar parks with aggregate sanctioned capacity of 39,188 MW. [2] Sanctioned capacity is not the same as commissioned capacity.
 

The Green Energy Corridor programme had enabled evacuation of approximately 24,567.8 MW of renewable capacity, with plans associated with about 44 GW of additional renewable-energy integration. Evacuation capability should not be counted as generation capacity.

 

The Pradhan Mantri Surya Sarovar Yojana was approved on 31 July 2026 with an objective of 5,000 MW of floating solar and at least 10,000 MWh of storage, supported by a reported outlay of Rs 5,070 crore. [2]
 

8. Where the opportunity may be

Developers

 

Developers can create value through low-cost capital, disciplined bidding, high availability, strong counterparties and control over land and connectivity. Track operating capacity, signed PPAs, tariffs, project returns, debt, receivables, CUF, curtailment and future equity requirements.
 

Manufacturers

 

Manufacturing earnings can be cyclical even when demand is growing. Track rated versus effective capacity, utilisation, sales volume, cell-to-module integration, technology, export mix, EBITDA per watt, inventory, receivables, capex and debt.

 

Rooftop, pumps and distributed solar

 

This segment benefits from government programmes and customer savings, but execution is fragmented. Distribution, installation quality, after-sales service, subsidy processing and working capital can become competitive advantages.
 

Storage and hybrid power

 

Storage becomes more valuable as solar penetration increases, but business models vary. Investors should check whether revenue comes from capacity payments, energy arbitrage, ancillary services or bundled renewable-power tariffs.

 

9. Selected listed-company research universe

 

This is a research starting point, not a recommendation and not an exhaustive list.

 

  • Tata Power: Development, EPC, rooftop, cells and modules. The key question is whether integrated growth can produce acceptable returns without excessive capital intensity.
  •  
  • Adani Green Energy: Utility renewable development and storage. Track leverage, tariff quality, execution and storage economics.
  •  
  • NTPC / NTPC Green Energy: Utility-scale renewable development. Track conversion of awarded and construction capacity into operating assets.
     
  • Waaree Energies: Modules, cells and manufacturing integration. Track utilisation and margins as domestic capacity expands.
     
  • Vikram Solar: Module manufacturing and planned integration. Track scale benefits, technology and balance-sheet risk.
     
  • Adani Enterprises: Integrated cell, module, ingot and wafer manufacturing. Track upstream utilisation and yields.
  •  
  • Reliance Industries: Integrated new-energy manufacturing. Track commercialisation and earnings materiality.
  •  
  • Borosil Renewables: Solar glass. Track demand, imports, duties, utilisation and spreads.

Selected company disclosures show why operating and planned capacity must be separated:
 

  • Tata Power reported 4.9 GW of integrated cell and module capacity and approved a phased 10 GW ingot-wafer investment in its FY2025-26 update. [9]
  • Adani Green reported 20.1 GW of installed renewable capacity and 3,551 MWh of commissioned BESS capacity for Q1 FY2026-27. [10]
  • Vikram Solar reported 9.5 GW of module capacity and a 10.6 GW order book as of 31 December 2025. [11]
  • Adani Enterprises reported 4 GW each of cell and module capacity and 2 GW of ingot-wafer capacity, while separately identifying planned expansion. [12]
  • Reliance reported its first 200 MWp of HJT module production and a phased ramp-up towards 10 GWp, with further expansion planned. [13]

Company releases are primary management disclosures, not independent research. Figures should be checked against the latest stock-exchange filing, annual report and quarterly investor presentation.
 

10. Major risks

 

  1. Aggressive tariffs can reduce project returns.
  2. Delayed PPAs, land, permits or transmission can postpone cash flow.
  3. DISCOM receivables can increase working-capital needs.
  4. Curtailment can reduce generation.
  5. Module oversupply can compress manufacturing margins.
  6. Technology changes can make new factories less competitive.
  7. Policy changes can alter domestic-content and import economics.
  8. Storage projects can face uncertain degradation and replacement costs.
  9. Large capex plans can increase leverage and equity dilution.
  10. Announced, awarded, under-construction and commissioned capacity can be mistakenly combined.

11. Investor checklist

 

  • What percentage of capacity is operating?
  • How much has a signed PPA and grid connectivity?
  • What is the expected equity return at the contracted tariff?
  • How much funding is still required?
  • Are receivables and working capital rising faster than revenue?
  • Is manufacturing capacity qualified and utilised?
  • Are margins dependent on temporary policy protection?
  • Is the company exposed to one technology, customer or geography?
  • Are expansion numbers plans or board-approved funded projects?
  • Does cash flow support the reported profit?

Conclusion

 

India's solar opportunity is real, but capacity growth alone does not guarantee shareholder returns. The strongest businesses are likely to combine execution, low financing cost, disciplined capital allocation, reliable technology and control over critical parts of the value chain.

For developers, the central question is return on invested equity. For manufacturers, it is profitable utilisation rather than announced gigawatts. For the wider system, storage and transmission are becoming as important as adding another solar plant.

The right approach is not "buy every solar company." It is to identify where durable cash flow, competitive advantage and balance-sheet discipline meet a long runway of demand.

Previous Parts in This Series

Want Access to Research-Led Market Insights?

You can explore my research plans here:

  • Momentum Edge Pack — Swing Trading: View plan
  • Tactical Growth Pack — Positional Trade: View plan
  • Equity Growth & Wealth Pack: View plan

Please review the plan details, suitability and risk disclosures before subscribing.

Disclaimer

This article is for education and research purposes only. It is not investment advice or a recommendation to buy, sell or hold any security. Solar-sector projects involve regulatory, construction, technology, funding and execution risks. Please conduct your own due diligence and consult a qualified financial adviser before making investment decisions.

Disclosure: The author, associates and relatives have no financial interest or holdings in the securities of the companies discussed in this article as of 8 September 2026.

 

Primary sources

 

  1. CEA: Installed Capacity Report, June 2026
  2. PIB: Solar Sector Review
  3. CEA: National Generation Adequacy Plan 2035-36
  4. MNRE/PIB: ALMM List-II Limited Relief Window
  5. MNRE/PIB: ALMM List-III
  6. MNRE: Solar PV PLI Scheme
  7. Ministry of Finance: Budget 2025-26 Customs Changes
  8. Ministry of Power: Revised RCO Notification
  9. Tata Power FY2025-26 Update
  10. Adani Green Q1 FY2026-27 Update
  11. Vikram Solar Q3 FY2025-26 Update
  12. Adani Enterprises Solar Manufacturing Review
  13. Reliance Industries Annual Report 2025-26